Happy FERC show-cause order week, to those who celebrate.
Our energy storage analyst, Lukas Karapin-Springorum, dove in and broke down what you need to know about all of them. Clients can access the full analysis on the platform here, or read on below for the highlights.
This is Currence’s weekly newsletter on the moves and motives shaping the load growth era. Not a subscriber yet?
Life in the fast lane
What happened
FERC directed the grid operators in its jurisdiction to act on large-load interconnection tariffs in June. That means defending, or rewriting, how loads of 50MW and above connect to the grid. And that sets how fast, and at what cost, data centers get power from 2028. Plus, it finally gives data centers the ability to trade firm service and Bring-Your-Own-Capacity (BYOC) for speed-to-power.
Now, after some back-and-forth, the filings are officially due this week. PJM, MISO, CAISO, NYISO, and ISO-NE filed new proposals in the past week. SPP files by tomorrow.
There’s a lot in there, and we read it so you don’t have to. Here’s the breakdown.
Make everything faster. Every filing makes non-firm connection or bring-your-own-capacity (BYOC) service the fast lane, but how firm service gets earned back varies.
All eyes have been on PJM, no surprise. Its new Fast Energization pathway starts allowing non-firm service by March 2027, for connections that accept curtailment risk rather than waiting for upgrades. (One of the reasons it’s able to move fast, mentioned in the filing, is because it’s leaning on Google’s Tapestry, whose tool is embedded in the interconnection process to process the volume.) Cluster studies under the new Fast Energization pathway will run annually starting November 2027. PJM doesn’t mention BYOC, though, but separately approved it for its own Reliability Backstop Procurement, in a separate docket, on November 9.
ISO-NE went furthest of anyone: it’s not procuring capacity for new data centers at all, so BYOC is the only route to firm service, full stop, with applications opening June 2027 for service in June 2028.
NYISO, on the other hand, is letting loads that create a reliability gap over 25MW bring their own capacity to jump the line.
Similarly, MISO’s bridge is Interim NITS, non-firm service for loads over 50MW available now while upgrades are pending; its permanent option, GRITS, would let those same loads get curtailed off real-time prices instead of a fixed schedule, but the software to run it won’t be ready until 2029. MISO already runs a separate studied BYOC batch process (LARS) for paired load-and-generation projects over 200MW.

At what cost.
Every ISO except SPP is making the data center carry the upgrade risk up front. Great for utilities, and worries about stranded assets.
PJM sets the strictest terms: no firm service without a 10-year Cost Recovery Agreement backed by a letter of credit covering 100% of projected charges.
MISO and NYISO lean on similarly long, security-backed commitments, MISO’s Total Required Revenue Commitment and NYISO’s 15-year recovery schedule.
CAISO requires security-backed minimum payments toward upgrades plus all local interconnection costs.
SPP takes a different approach. Costs above $500k/MW (under 50MW) or $25m (over 50MW) get assigned directly to the interconnecting utility, not the data center, which then likely passes the bill through via retail contract.
And throw in a little flexibility.
Ride-through and ramp rate rules came up in almost all of the filings.
PJM, MISO, and CAISO all committed to specific ramp rate caps, 30MW/minute for MISO, 20MW/minute over a 10-minute window for CAISO, with SPP already enforcing 20MW/minute since January.
ISO-NE and NYISO are holding out. Both are still developing their ride-through and ramp rate rules through stakeholder processes with no committed timeline yet.
Flexibility is showing up in every filing rebranded as bring your own capacity, non-firm service, curtailment, interim, and price-responsive load.
Lukas’ take
FERC laid down the large load law. It said, take a good, hard look at your rules and fix them where they don’t make sense, or we’ll fix them for you.
Regional grid operators came to the table in a relatively timely fashion, with well-thought-out responses that fit their regions. Each handled differently, shown by the range of responses. But overall, the market is finally moving away from the workarounds and mechanisms that were not fit for the largest of large loads (data centers), and finally writing tariffs and market rules sized for this new moment, with guardrails for affordability.
It’s been obvious that building new generation and transmission to serve this load is slow and expensive. But there hasn’t really been a way to pursue the fastest, cheapest option, to just build less of it. But now, new flexibility rules. Powering new data centers with electrons from increased system utilization, or behind-the-meter or co-located configurations. All of the “non-firm service” for interconnection.
Non-firm service for interconnection speed is a fundamental departure from how utilities have always served large loads. It could be just a bridge mechanism, still a great option now on the table. Steep deposits will gate the queue before reaching interconnection agreements that require collateral and give operations teams power, except during curtailment events that could last 8h+ by 2035.
Access to power has already started separating the serious players from the dreamers, and the proposed changes will widen the gap. This will thin the speculative crowd.
Net good for AI. Net good for business. Net <insert your opinion here> for all of us as humans.
Who this helps
Ratepayers. ISOs are making official what utility large load tariffs had already started: data centers will be on the hook for grid upgrades. Collateral makes sure of that, whether they use the power for 20 years or fold in the next 2 years.
The flexible data center layer. Data centers on a non-firm connection need a plan for curtailment events that includes some combination of workload shifting and behind-the-meter energy assets like storage or generation. All of that needs to be built, integrated, and managed. Boom times for the likes of Emerald, Calibrant, DG Matrix, and Hammerhead.
Storage developers and OEMs. I might be biased, but I think non-firm service will mostly be backed by lithium-ion storage because it’s fast, scalable, and long-enough duration. SPP, MISO, and PJM, not exactly hot storage markets, are suddenly open for business. Jupiter Power just locked up another 16GWh of FEOC-compliant supply to feed the wave of demand.
Who should be nervous
The climate. Non-firm interconnection is fast and cheap because it increases utilization of the existing grid and generation fleet instead of building more assets. The extra electrons come from running the coal and gas fleet at a higher capacity factor.
Data center operators who are making it up as they go along. Even if they can get connected, ramp-rate limits will bind from 2027. Unmitigated load swings might’ve flown under the radar in the past, but now operators have to pull it together or get disconnected. There is no easy fix, only complex electrical engineering to stitch together the available technologies.
The full research breaks down every ISO’s non-firm and BYOC mechanics. Clients can read it on the platform here.
Meter reading (13 - 19 Nov)
A quick read on the numbers shaping the market. The capex, the contracts, the regs, all anchored in the so-what.
50MW // Google signed Quaise Energy’s first commercial offtake, buying power from Project Obsidian, Quaise’s superhot-rock well on Newberry Volcano, to feed three Google data centers in The Dalles, Oregon. First power is targeted by 2030, and Quaise still has to build a 10-mile line from the well to a substation in La Pine. Google is branching out in its geothermal picks beyond Fervo, and it’s usually pretty good at picking winners.
$10m // Voltus bought Stem’s Athena battery optimization platform in cash, and launched a network of nearly 40 battery companies, with Branch Energy, Scale Microgrids, and Sparkfund named so far. Voltus needs more batteries under management to back the gigawatt VPP it’s running for Google in PJM. Consolidation could keep going as aggregators like Voltus pick up momentum and cash.
3GW // Utah’s Carbon County planning commission voted to give Valar Atomics a conditional use permit for its Raceway Energy Campus. The 640-acre site on state trust land would run on gas first and eventually on 40 to 120 small reactors, with no public hearing required and no tenant, offtaker, or capex disclosed. It still needs an air permit from Utah and an NRC construction permit.
On the docket
The policies, rulings, and company moves worth watching.
Anthropic starts trading on Nasdaq today under ticker ANT. Shares are priced at $70 to $78, and the open is the market’s first live verdict on the gas-heavy buildout we covered last issue, a test that matters more with Jensen Huang out as Nvidia CEO since last week. We’re watching what holds.
BAAJA cleared its first Senate hurdle, 73-25. The Senate invoked cloture on the motion to proceed to the permitting bill on November 9, which would require data centers to bear the grid costs they cause, but it still needs further floor votes and House passage before it’s law.
ERCOT’s Batch Zero verification comes due December 10. The grid operator has to file its Eligibility Verification Report and Community Impact Review Report by then, deciding which large loads survive Governor Abbott’s audit. Then, Governor-elect Hinojosa will take over January 19, after campaigning on freezing rates until data centers pay their own way.
Plenty of solid-state transformer announcements. Tesla’s Powercore, a 7.4MW unit combining a transformer, inverter, and breaker, launched at RE+ 2026, chasing the transformer-backlog bottleneck slowing data center interconnection. Vertiv introduced its own 5MW PowerNexus MV SST the same week at SC26, converting medium-voltage AC straight to 800VDC in one stage. LG Energy Solution is showing an integrated AIDC power platform at RE+ alongside next-gen BESS, though its sodium-ion work is a separate track.
New Jersey’s BPU made VPPs a utility mandate. It ordered Atlantic City Electric, JCP&L, PSE&G, and Rockland Electric to stand up interim PowerUp NJ programs by 1 October 2027, pooling home batteries, thermostats, and other customer devices to cut peak demand across the four utilities.
New & upcoming at Currence
The latest research, features, and data drops on the Currence platform.
Off-grid data centers are running years behind schedule in ERCOT. Currence tracked all off-grid data center projects in Texas, and found that they likely won’t deliver on time because they’re waiting on turbines and engines, with Texas’s permit pause adding a second bottleneck. Read the full ERCOT off-grid forecast.
ISOs’ FERC show-cause responses open non-firm and BYOC routes to data center interconnection. Our breakdown covers all six ISOs, docket by docket, with the exact non-firm and BYOC mechanisms, the cost allocation rules that could add tens of millions in upgrade costs, and the ramp-rate mandates about to become law in three major markets. See which developers get a fast lane to 2028 energization, which players are positioned for the upside, and which ones get priced or regulated out. Read it here.
The B-side
So, there were a handful of you who didn’t like my pick last week – tough, lol. I stand by it. 🤓
Okay, so back in college, most Sunday afternoons you’d find me driving into Provo Canyon in Utah for a short hike in the mountains. Invariably, I’d listen to this show, Saint Paul Sunday, where the host would bring classical musicians into his studio, and they’d play and talk.
One week, he had Kronos Quartet on. They played a song, Flugufrelsarinn, by Sigur Rós. I’d never heard the song before, and I’ve never heard anything like it since. I loved it so much that in grad school, I went to NYC for a Kronos concert at Carnegie Hall, just to hear this piece. The original, that I only heard years later, is also incredible.
I’m actually going to add two this week. I’m in Las Vegas for RE+. It’s been a great week – thanks to those who came to the dinner we co-hosted with Antenna Group! – but has also got me feeling so close, yet so far, from the mountains. The mountains win again.